A White House-appointed review committee has found that NASA's
current exploration budget falls nearly
$30 billion short of being able to pay for the lofty lunar goal. The
committee will file a final report on its review of NASA's human spaceflight
plans by Aug. 31, and has drawn four potential future options to be considered
by President Barack Obama.
Only one of those options includes the Ares I
rocket, which is a two-stage rocket made up of a solid-fueled first stage and a larger, liquid-fueled upper stage.
NASA officials told SPACE.com that the options put forth by
the committee will not immediately affect plans for the Ares I-X test flight. Only
with direct instruction from the Obama Administration can the agency shift its
current exploration plan and test regime, they said.
Critical test ahead
The Ares I-X rocket is not a full
version of the Ares I booster. It carries a dummy upper stage and Orion
mass simulator. It also includes a fake fifth segment of its five-piece first
stage, which is derived from the four-segment solid rocket boosters used to
launch space shuttles.
After launch, the first stage is expected to fall away and parachute
down to the Atlantic Ocean to be recovered, while the dummy second stage and
attached Orion and abort tower simulators crash into the ocean further downrange.
The Ares I-X should reach an altitude of about 25 miles (40.2 km) in roughly
two minutes after liftoff, mission managers have said.
Engineers have attached 700 sensors to the test rocket and
will perform a series of systems checks over the next few weeks to be sure the
Ares I-X is ready to fly. They will also perform a so-called "modal test" to gently
shake the tall, slender rocket in a stiffness test, NASA officials said.
NASA's goals for the Ares I-X flight are to prove the
stability of the Ares I rocket stack, which has a fatter second stage perched
atop a skinny first stage, as well as test ground processing and launch pad operations.
Excessive vibrations have also been a concern with the Ares
I rocket that prompted engineers to come up with a shock absorbing system to
dampen the worst of the shaking. So NASA hopes the upcoming test will yield new
insight into booster's stability and performance during first-stage separation.
According to
NASA's current plan, the Ares I-X rocket would roll out to the seaside Pad 39B
launch site – a modified shuttle launching pad – four days before its planned
liftoff, NASA spokesperson Allard Beutel.
The Ares I-X flight is the first in a series of test
launches for Ares I and Orion vehicles. The first test firing of a full five-segment Ares I first stage motor is scheduled for Aug. 27.
Three abort system tests are planned
between now and 2012, as well as a follow-up Ares I-Y test and the first
integrated test of Ares I and an Orion vehicle (called Orion I) in 2015. But
the demonstration launch has been plagued by months of delays due to technical challenges.
Beutel said that, barring any unforeseen glitches, Ares I-X
engineers are currently on track for the Halloween launch test.
"If the
loads testing goes well, then we should be able to make the Oct. 31 target,"
Beutel said.