WASHINGTON --
NASA sent Congress a revised spending plan for 2005 that would significantly
cut the Project Prometheus nuclear power and propulsion program, cancel a host
of international space station-based biological and physical research
activities, and postpone some space science missions, including two advanced
space telescopes and a Mars science lander slated to
launch in 2009.
The cuts were
necessary, according to NASA, to pay the remaining $287 million tab for
preparing the space shuttle for its return to flight, to make a substantial
down payment on a potential Hubble Space Telescope servicing mission, to
accommodate $400 million worth of special projects that lawmakers added to
NASA's budget last year, and to cover larger than predicted bills for a variety
satellite projects being prepared for launch.
NASA informed
Congress of these intended changes in an updated 2005 Operating Plan sent to
Congress May 11. A copy of the operating plan, obtained by Space News,
details changes both big and small that NASA says it needs to make to its $16.2
billion budget 2005 to get through the end of the fiscal year.
NASA's latest
operating plan includes the full $291 million Congress directed it to spend
this year preparing for a possible Hubble servicing mission. NASA's last
spending plan, sent to Congress in December for review, allocated only $175
million of that amount to a Hubble mission. In February, NASA announced, to the
chagrin of Hubble-supporters in Congress, that it would abandon any effort to
save Hubble.
Since taking
over as NASA administrator last month Mike Griffin has reversed that decision
and ordered engineers at Goddard Space Flight Center to start preparing a
Hubble servicing mission on the assumption that one will ultimately go forward.
A formal decision is expected after the shuttle makes its return to flight.
Griffin
explained his rationale in a May 10 letter accompanying the operating plan,
saying that funding return to flight, Hubble servicing, programmatic overruns
and releasing the $400 million in congressional earmarks "has created some
difficult choices" for NASA.
"Given a
choice, my preference as Administrator is to eliminate lower-priority programs
rather than reducing all programs in the face of budget difficulties, to
maintain efficient execution of the programs which remain," Griffin wrote
lawmakers. "Delays and deferrals inevitably lead to increased life cycle costs
and erode the overall performance of the Agency's programs. Thus, NASA must set
clear priorities to remain within the budget which has been allocated."
Cut from
NASA's latest operating plan are about $160 million worth of space
station-based biological and physical research efforts that a recently
completed, although unreleased, NASA review concluded were unnecessary in light
of NASA's new focus using the space station for research that directly serves
the needs of its space exploration goals.
While that is
bad news for fundamental biological and physical research, some newly
identified high priority areas of investigation will receive more money in the
months and years ahead, according to Griffin.
"These high-
priority areas include space radiation health and shielding, advanced
environmental control and monitoring, advanced extra-vehicular activities,
human health and countermeasures, advanced life support, exploration medical
care, and space human factors," Griffin wrote.
"The highest priorities for research on ISS have been identified as medical
research with human subjects and microgravity validation of environmental
control and life support technologies. Lower-priority tasks, which are now
subject to reduced funding, include basic research using model organisms
(such as cells or rodents), and fundamental research in physics, material
science, or basic combustion - with no direct link to exploration
requirements."
NASA also
plans to refocus Project Prometheus on the development of "space-qualified
nuclear systems to support human and robotic missions" especially those needed
to support NASA's near term exploration goals. NASA started the program known
as Prometheus in 2002 to develop nuclear power and propulsion systems for deep
space probes like the Jupiter Icy Moons Orbiter, a flagship-class mission that
NASA deferred indefinitely earlier this year once it became clear that the
undertaking would cost tens of billions of dollars and not necessarily help
NASA accomplish its goal of returning to the Moon and sending humans to Mars.
The operating
plan sent to Congress would cut $171 million from the Prometheus budget,
leaving the program with $260 million for the time being.
Money for the
Crew Exploration Vehicle, meanwhile, would remain untouched at $421.9 million
for the year, even though NASA has said it intends to
accelerate the program in order to minimize any gap between retiring the
shuttle in 2010 and fielding the new system. NASA is still evaluating its
options for accelerating the program, but has already announced that it intends
to pick the contractor it wants to build the system in early 2006 instead of
late 2008.
In addition
to the cuts and increases, the operating plan also indicates that NASA intends
to take planning for a Hubble servicing mission away from its Exploration
Systems Mission Directorate and give it back to the Science Mission Directorate.
Exploration Systems, however, picks up full responsibility
for NASA's nascent Lunar Robotic Exploration Program and the ISS Crew and Cargo
Services effort to find alternatives to the space shuttle for delivering cargo
and potentially people to the space station. That effort, initiated in
2004, had been under the management of the Space Operations Mission
Directorate, which is in charge of the shuttle and station programs.
NASA would
also delay the Space Interferometry Mission and
Terrestrial Planet Finder, two advanced space telescope projects slated to
launch some time after the James Webb Space Telescope. Griffin's letter also
says that NASA is considering delaying the Mars Science Laboratory mission from
2009 to 2011. NASA's operating plan cuts nearly $72 million from the program.