1 of 37
Atlantis Gets Its Name
Credit: Boeing
The space shuttle Atlantis gets its name at Rockwell's Palmdale plant in this image from March 15, 1985.
2 of 37
Atlantis' Upper Forward Fuselage Canopy
Credit: Boeing
Atlantis' upper forward fuselage canopy is seen in this photo that was taken on Aug. 5, 1982 at the Rockwell International facilities.
3 of 37
Shuttle Engineers Work on Atlantis' Aft Fuselage
Credit: Boeing
Shuttle engineers at Rockwell work on the initial fabrication and assembly of Atlantis' aft fuselage in August 1982.
4 of 37
Atlantis' Crew Module in Transit
Credit: Boeing
Shuttle Atlantis' crew module is transported to Rockwell's vacuum chamber test cell, at the Downey facility on March 31, 1983.
5 of 37
Atlantis' Upper Forward Aft Fuselage Assembled
Credit: Boeing
An upper section of the shuttle Atlantis' aft fuselage is being assembled in this photo that was taken on Aug. 5, 1982.
6 of 37
Atlantis' Vertical Stabilizer Delivery
Credit: Boeing
Atlantis' tail section, which is also called a vertical stabilizer, is delivered to the Rockwell plant for assembly in Aug. 1982.
7 of 37
Vacuum Test on Atlantis' Crew Module
Credit: Boeing
Atlantis' crew module is carefully installed into the vacuum chamber test cell at Rockwell's plant in this photo from March 31, 1983.
8 of 37
Engineers Watch Atlantis' Vertical Stabilizer Delivery
Credit: Boeing
Engineers look on during the delivery of Atlantis' vertical stabilizer tail section.
9 of 37
Atlantis' Payload Bay Doors Delivery
Credit: Boeing
Atlantis' payload bay doors were delivered to Rockwell's Palmdale, Calif. facility from Tulsa, Okla. This photo was taken on Sept. 9, 1982.
10 of 37
Atlantis' Payload Bay Door Delivery
Credit: Boeing
One of Atlantis' payload bay doors is seen in this image from its delivery to Rockwell's Palmdale plant in Sept. 1982.
11 of 37
Atlantis' Fit Check
Credit: Boeing
Engineers and technicians perform a fit check of Atlantis' upper forward fuselage and lower forward fuselage with the crew module installed in this photo from Jan. 12, 1983.
12 of 37
Atlantis' Left Wing Panel Installation
Credit: Boeing
Installation of a panel on Atlantis' left wing continues at Rockwell's Palmdale plant on Oct. 26, 1982.
13 of 37
Atlantis' Left Wing Glove Inspected
Credit: Boeing
Engineers inspect Atlantis' left wing glove prior to its installation. This photo was taken at Rockwell's Palmdale facility on Oct. 12, 1982.
14 of 37
Inital Fabrication and Assembly of Atlantis' Upper Fuselage
Credit: Boeing
The initial fabrication and assembly of Atlantis' upper fuselage continues at the Rockwell Downey facility on Sept. 21, 1982.
15 of 37
Atlantis' Engineers From Above
Credit: Boeing
An overhead shot of shuttle engineers as they prepare to install Atlantis' right inboard elevon at Rockwell's Palmdale facility on Nov. 22, 1982.
16 of 37
Preparations Continue
Credit: Boeing
Preparations continue on Atlantis' aft fuselage for its delivery to Rockwell, Palmdale from Rockwell, Downey in May 1983.
17 of 37
Construction Underway
Credit: Boeing
Construction of Atlantis' lower forward fuselage was well underway on Nov. 8, 1983 at Rockwell's Palmdale plant.
18 of 37
Atlantis' Aft Fuselage Prepared for Delivery
Credit: Boeing
Engineers prepare Atlantis' aft fuselage for delivery to Rockwell's Palmdale facility from the Downey plant on May 21, 1983.
19 of 37
Assembly of Atlantis' Forward Reaction Control System
Credit: Boeing
Atlantis' forward reaction control system is assembled at Rockwell's Palmdale facility in this photo from Oct. 6, 1983.
20 of 37
President Reagan with Atlantis
Credit: Boeing
President Reagan stands in front of Atlantis' aft fuselage at Rockwell's Downey facility in this photo from May 25, 1982.
21 of 37
Atlantis' Delivery from Palmdale
Credit: Boeing
Atlantis' mid fuselage is delivered to Rockwell's Palmdale plant from General Dynamics.
22 of 37
Atlantis' Crew Module Prepped for a Vacuum Test
Credit: Boeing
Atlantis' crew module is moved to the vacuum chamber test cell at Rockwell's Downey facility on March 30, 1983.
23 of 37
Atlantis Gets Thermal Tiles
Credit: Boeing
Thermal tiles are installed on Atlantis' right-hand wing glove at Rockwell's Palmdale facility on Jan. 18, 1983.
24 of 37
Installation Continues on Atlatnis' Thermal Protection System
Credit: Boeing
Work continues on installing part of Atlantis' thermal protection system on the left-hand mid fuselage. This image was taken on Jan. 6, 1983 at Rockwell's Palmdale plant.
25 of 37
Fuselages Unite
Credit: Boeing
Atlantis' lower forward fuselage and mid fuselage are seen attached to one another at Rockwell's Palmdale facility on Nov. 9, 1983.
26 of 37
Atlantis' Crew Module Connected to Fuselage
Credit: Boeing
Atlantis' crew module is installed and attached to the shuttle's lower forward fuselage at Rockwell's Palmdale plant on April 12, 1984.
27 of 37
Atlantis Starts Taking Shape
Credit: Boeing
Atlantis starts to take shape, as engineers continue work to install the shuttle's crew module, lower forward fuselage and mid fuselage at the Palmdale plant on April 12, 1984.
28 of 37
Atlantis' Upper Fuselage Installed
Credit: Boeing
The upper fuselage is being installed onto Atlantis' lower fuselage, with the crew module already secured. This photo was taken at Rockwell's Palmdale facility on April 25, 1984.
29 of 37
Construction of Atlantis' Nose Cap
Credit: Boeing
Construction of Atlantis' nose cap continues at Rockwell's Palmdale facility on July 11, 1984.
30 of 37
Atlantis' Assembly Complete
Credit: Boeing
With Atlantis' assembly complete, the shuttle is rolled out from Rockwell's Palmdale plant on April 9, 1985.
31 of 37
First Peak
Credit: Boeing
Spectators look on as Atlantis rolls out from the Rockwell's Palmdale facility to NASA's Dryden Flight and Research Facility on April 9, 1985.
32 of 37
Moving Day
Credit: Boeing
Upon completion of Atlantis' assembly, the new orbiter is moved from Rockwell's Palmdale facility to NASA's Dryden Flight and Research Facility on April 9, 1985.
33 of 37
On the Move to Dryden
Credit: Boeing
Basked in sunlight, Atlantis is rolled to NASA's Dryden Flight and Research Facility on April 9, 1985.
34 of 37
Atlantis' Transport to Dryden
Credit: Boeing
Atlantis is transported from Rockwell's Palmdale plant to NASA's Dryden Flight and Research Facility in this photo from April 9, 1985.
35 of 37
Make Way
Credit: Boeing
Space shuttle coming through! The newly constructed shuttle Atlantis is transported from Rockwell's Palmdale plant to NASA's Dryden Flight and Research Facility in this photo from April 9, 1985.
36 of 37
A Historic Journey
Credit: Boeing
With its assembly complete, Atlantis makes its historic journey from Rockwell's Palmdale plant to NASA's Dryden Flight and Research Facility on April 9, 1985.
37 of 37
A Long Awaited Arrival
Credit: Boeing
Atlantis arrives at NASA's Dryden Flight and Research Facility on April 9, 1985.












































































