WASHINGTON -- A flight-demonstration sensor for the
next-generation of U.S. polar-orbiting weather satellites sustained damage during
testing Oct. 11, but program officials said the mission's launch schedule
should not be affected.
The sensor, dubbed the Cross-track Infrared Sounder, was
damaged during acceptance testing at the Ft. Wayne, Ind., facilities of its
builder, ITT Corp. The sensor is part of the payload package aboard a precursor
satellite to the U.S. civil-military National Polar-orbiting Operational
Environmental Satellite System, or NPOESS.
The precursor mission, a multi-agency effort known as the NPOESS
Preparatory Project (NPP), is scheduled to launch in September 2009.
Government and industry program officials said the mishap, which occurred during
a vibration test meant to prove the instrument is tough enough to survive
launch, appeared unlikely to delay NPP's liftoff.
U.S. Air Force Col. Dan Stockton, the NPOESS program
director, acknowledged Oct. 19 in a brief written statement that the
Cross-track Infrared Sounder had been damaged and vowed that it would be fixed.
"Any problem of this nature is serious. We have deployed
resources of the [Departments of Commerce and Defense] and NASA to work with
the contractor team to evaluate and fix the problem," Stockton said.
NPOESS is a joint effort of the Air Force and National
Oceanic and Atmospheric Administration, with NASA as the junior partner. NASA has the
lead in the NPP mission. Andrew Carson, the NASA program executive for the NPP
and NPOESS programs, told Space News in an Oct. 19 e-mail that if the NPP
mission does fall behind schedule, the setback with the Cross-track Infrared
Sounder probably would not be to blame. He said the NPP's current launch date,
a full three years later than originally planned, is driven primarily by how
long it takes to complete one of the spacecraft's other instruments, the
Visible Infrared Imaging Radiometer Suite.
"Delivery of the Visible Infrared Imaging Radiometer Suite
is on the critical path for the launch of NPP in September 2009," Carson said
in his e-mail. The Cross-track Infrared Sounder "vibration failure review team
is taking a cautious, methodical approach to determine the root cause of the
failure. It is too early in the investigation to say how much redesign or
rework will be necessary, however it is not expected that the delivery of the...
flight unit will slip beyond the delivery of" the Visible Infrared Imaging
Radiometer Suite.
That instrument, being built by El Segundo, Calif.-based
Raytheon Space and Airborne Systems, has been widely labeled the driving factor
behind the NPOESS cost and schedule problems leading up to the decision to
restructure the program.
Sally Koris, a spokeswoman for NPOESS prime contractor
Northrop Grumman Space Technology of Redondo Beach, Calif., said in an Oct. 19
e-mail that the test setback is expected to have minimal impact on completion
of the NPP spacecraft.
"Based on the information we have at this time, we believe
there is sufficient margin in the program's schedule to accommodate analysis
and repair of the sensor prior to its required delivery date to NPP," Koris
wrote. "Meanwhile, a flight-like... engineering development unit will be used to
test and verify mechanical and electrical interfaces between the sensor and the
spacecraft."
The NPP spacecraft is being built by Boulder, Colo.-based
Ball Aerospace and Technologies Corp. under contract to NASA. Northrop Grumman
is overseeing development of NPP's instruments since subsequent models will fly
aboard the NPOESS satellites, which are slated to start launching in 2013.
Koris said in her e-mail that the Cross-track Infrared
Sounder "was undergoing a planned series of acceptance tests when it sustained
structural damage in the instrument frame." She said review boards made up of
government and industry personnel have been convened to investigate the
incident and "determine if this is a manufacturing problem, a test
configuration or test fixture problem, operator error or a design issue."
Bernice Borrelli, a spokeswoman for Rochester, N.Y.-based
ITT Space Systems Division, said in an e-mail that the sensor development
program "will incur a schedule movement but it will not impact the NPP
schedule."
Ball Aerospace spokeswoman Roz Brown said Oct. 19 that prior
to the testing incident Ball expected to take delivery of the sounder Jan. 3
and begin integrating it with the NPP spacecraft bus around Jan. 10. She said
Ball Aerospace also does not expect the setback to impact NPP's launch schedule
but was awaiting NASA's assessment of the situation.