1 of 19
Endeavour's Crew Module During Early Construction
Credit: Boeing
The crew module initial build takes place in Bldg 290 high bay at the Rockwell Downey facility on June 12, 1986.
2 of 19
Endeavour's Crew Module Being Constructed
Credit: Boeing
The crew module initial build continues in Bldg 290 high bay at the Rockwell Downey facility on July 18, 1986.
3 of 19
Vacuum Test
Credit: Boeing
The crew module is being lowered into the vacuum chamber test facility at the Rockwell Downey facility on January 20, 1987.
4 of 19
Endeavour Mid-fuselage Delivery
Credit: Boeing
The mid-fuselage is being delivered from General Dynamics (San Diego) to the Rockwell Palmdale facility on September 10, 1987.
5 of 19
Endeavour's Vertical Tail Delivery
Credit: Boeing
The vertical tail is being delivered from Fairchild (New York) to the Rockwell Palmdale facility on September 18, 1987.
6 of 19
Endeavour's Crew Module Lowering
Credit: Boeing
The crew module is being lowered into the lower forward fuselage at the Rockwell Palmdale facility on January 20, 1988.
7 of 19
Endeavour's Left Wing Positioning
Credit: Boeing
The left wing is being positioned for installation onto the mid-fuselage at the Rockwell Palmdale facility on February 19, 1988.
8 of 19
Endeavour's Right Wing Installation
Credit: Boeing
The right wing is being installed onto the mid-fuselage at the Rockwell Palmdale facility, Calif., on February 19, 1988.
9 of 19
Endeavour's Aft Fuselage Roll Out
Credit: Boeing
The aft fuselage is being rolled out of the Rockwell Downey facility prior to delivery to the Rockwell Palmdale facility, Calif., on August 15, 1988.
10 of 19
Endeavour's Manifolds Installation
Credit: Boeing
The Liquid Hydrogen (LH2) and Liquid Oxygen (LO2) manifolds installation in the aft fuselage at Rockwell Downey facility, Calif. on August 2, 1989.
11 of 19
Endeavour's Aft Fuselage Preparation
Credit: Boeing
The aft fuselage is being prepared for shipment at the Rockwell Downey facility to be delivered to Rockwell Palmdale facility on December 12, 1989.
12 of 19
Endeavour's Aft Fuselage Installation
Credit: Boeing
The aft fuselage is being installed onto the mid-fuselage at the Rockwell Palmdale facility on December 20, 1989.
13 of 19
Endeavour's Forward Fuselage/Crew Module Delivery
Credit: Boeing
The forward fuselage/crew module is being delivered to the Rockwell Palmdale facility on February 23, 1990.
14 of 19
Endeavour's Forward Fuselage/Crew Module Installation
Credit: Boeing
The forward fuselage/crew module is being installed in the Rockwell Palmdale facility on February 28, 1990.
15 of 19
Endeavour's Tail Installation
Credit: Boeing
The vertical tail is being installed in the Rockwell Palmdale facility on August 27, 1990.
16 of 19
Endeavour's Payload Bay Doors Installation
Credit: Boeing
This image shows the payload bay doors being installed in the Rockwell Palmdale facility on September 9, 1990.
17 of 19
Endeavour Mates to the Shuttle Carrier Aircraft
Credit: Boeing
OV-105 Endeavour is mated to the Shuttle Carrier Aircraft (SCA) at Rockwell Palmdale facility on May 1, 1991.
18 of 19
Endeavour's Roll Out
Credit: Boeing
OV-105, Endeavour rolled out at Rockwell Palmdale facility, Calif. on April 25, 1991.
19 of 19
Endeavour's Roll Out from Above
Credit: Boeing
This image shows OV-105 being rolled out after the build at the Rockwell Palmdale facility on April 25, 1991.








































