The problem of actual costs of space
infrastructure overrunning estimated costs - often by large amounts - is one of
the most chronic challenges in our space community. In the July 16 issue of Space
News, for instance, articles addressed costs in excess of
estimates for projects including NASA's Orbiting Carbon Observatory and the Kepler telescope, and the U.S. Air Force's Space Based
Infrared System. These are but three examples of many others. In
fact, overruns are almost the rule rather than the exception - when was there
last an article about a project within its estimated budget? Or,
for that matter, under budget? But before heading to the woodshed for 30 lashes, a word or two of perspective may be in
order.
Ideal cost estimation, the perfect
process that encounters no technical, time or other
problems, has eluded all humankind. Stanley Engerman
of the University of Rochester and Kenneth Sokoloff of
the University of California, Los Angeles, have
evaluated a dozen major U.S. public works projects, including construction of the Erie Canal, the
interstate highway system, the original Superdome and Boston's Big
Dig. The ratio of actual to projected cost in these examples ranges from about
1.1 to 20; for seven of the 12 the ratio is greater than 2.
In a
November 2006 report, "Space
Acquisitions: DoD Needs to Take More Action to
Address Unrealistic Initial Cost Estimates of Space Systems," the U.S. Government
Accountability Office (GAO) found current cost estimates had increased in the
range of 44 percent to more than
double original estimates for six ongoing space programs. Similarly, a 2004 Congressional
Budget Office (CBO) report, "A Budgetary Analysis of NASA's New Vision for Space
Exploration," found wide disparities between projected and actual costs in more than 70 space projects undertaken between 1977
and 2000.
Is the
problem endemic to public works - the canals, roads and space
projects undertaken and managed by government? Is there no problem in private
projects? Hardly - just ask commercial real estate developers or the neighbors down the street renovating their home or
building a new one.
Neither is the problem unique to the
United States. Large cost overruns plagued construction of the Euro tunnel, the
reconstruction of London's Wembley Stadium and the
building of a large oil pipeline from the Caspian Sea to a Mediterranean port,
a project undertaken jointly by Azerbaijan, Georgia and Turkey. In
a 2003 study of 258 rail, road and airport construction
projects in 20 nations, Danish researchers at the Delft University of
Technology in the Netherlands found substantial cost escalation to be the rule,
not the exception. And as readers of Space News well know, cost estimation
challenges all international space organizations, not just our own.
The reasons for these results are
several:
§
Engineering the uncertain: Uncertainty is inherent in new technology,
making it difficult to estimate costs of unknowns. Professors James Quirk and Katsuaki Terasawa have dubbed the
problem "pioneering bias in cost estimation" - the tendency for engineers and
other experts to mis-estimate the cost of developing
and testing out new technology. Of course, unexpected problems also arise even in
dealing with proven technology such as plumbing repairs in old houses, or a highway corridor
encountering a sacred ancient burial ground. Uncertainty by itself does not imply bias
in one direction. But Quirk and Terasawa find
that the tendency is to underestimate expected costs, which can lead to cost escalation, delays and outright
cancellation of projects.
§
The difficulty of monitoring to
avoid excessive profits, waste, fraud and inefficiency: These suspicions are at the very
heart of contracts, whether for major weapons procurement, highway construction or that extra
bathroom. The problem largely arises from asymmetric information and the
inability to monitor a contract. We - or governments acting on our
behalf - enter into a contract because the contractor has the information,
specialized knowledge, equipment and other required
inputs. In addition, it is difficult to audit the
contractor's every action. For these reasons, what constitutes excessive
profit, waste, fraud and
inefficiency is often a matter of "they said, we said; we did, they didn't."
§
Pressures to underestimate costs: Such pressures can arise among
competing programs within an agency or in the agency's relationship in
advancing proposals before congressional funders. The
GAO has found repeatedly in its interview-based and other studies that programs
"produce optimistic estimates in order to gain approval for funding." The Danish
researchers mentioned
above studying transportation infrastructure found "grossly inaccurate"
estimates over 70 years' of data, prompting them to write a strongly worded conclusion: The inaccuracy was by and large due to "strategic misrepresentation,
that is, lying." A researcher at the Harvard Business School offers a more
gentile description of this tendency - which is prevalent in the private sector
as well - dubbing it "self-serving bias."
§
Reputations don't matter: If a contractor repeatedly lowballs
estimates and incurs large overruns in actual costs, customers can spread the word.
But if choice among contractors is limited, or government program managers
repeatedly underestimate costs but are hard to fire, then the market discipline
of a good reputation is limited. Consolidation has lessened competition within
the traditional aerospace industry, blunting the effect of a bad reputation or,
as important, rewarding a good reputation.
So is there
anything to be done to improve cost estimation? Beware of any simple answer.
Cost estimation and its related domain, contract theory, have some
counterintuitive results. For instance, there are circumstances under which an
incomplete contract (and provisional cost estimation) is a good idea. In this
case, the parties to a contract prefer not to iron out all the details - that is, all the
variables that may affect the conditions of the contractual relationship. In a
study of the procurement of aircraft engines, researchers found that the cost
of writing and enforcing a contract to cover all contingencies and eventualities
in long-run projects was simply too expensive. The best contract leaves open
some issues for future negotiation.
That said,
some rules of the road include:
§
Demand information about a project's
benefits, not just its costs. Imperfect cost estimates or excessive actual cost overruns still may result in programs that are effective in
serving the public. In other words, cost growth per se is not an indicator of a
socially undesirable program, nor would a project that is completed within its
anticipated budget necessarily be an indicator of a socially desirable program. Decision-makers should require objective estimates
of the putative future benefits of a project as well as its costs.
§
Discourage precision. Program managers, agency heads,
budget managers and Congress
should refuse point estimates and narrow ranges of estimates. They should
tolerate and even demand uncertainty, requiring agencies to apply decision
software and analytical approaches that transparently communicate confidence
intervals and other related measures. What are the greatest risks in a project
and how will they be managed? Much like a mutual fund
manager, can government better act on behalf of the taxpayer to demand explanation
of the upside and the downside of public investments?
§
Keep the fox out of the henhouse. Objectivity in cost estimation is
hard to obtain. Engaging teams of private-sector analysts, provided they are
individuals with their own professional reputations at stake, may be workable.
Put their names - not their companies' - on the public report; much as under
the new Public Company Accounting Reform and Investor Protection of Act of 2002,
known to most of us as Sarbanes-Oxley, chief executives now personally sign and certify
financial reports.
§
Maintain a public track record. Which government program managers continue
to validate projects with large cost overruns, and which deliver better ratios
of actual to projected costs? When better ratios are obtained, we need to make
national heroes of our government program managers, who all too often receive
too little credit for good work but much notoriety when something goes awry.
§
Reward good results. When projects come in below budget,
savings are siphoned off for other things. For NASA centers, this perverse
incentive could be eliminated by establishing a virtual bank in which projects
that come in under projected cost keep the savings. These funds could be
carried forward within the scientific domain - for example, savings on one
telescope go into a pool to finance the next-generation telescope. Several years ago, NASA funded
researchers at California Institute of Technology and Purdue University to experiment with how to
design such a scheme. It's worth revisiting.
Molly Macauley
is a senior fellow at Resources for the Future. Prabirendra Chatterjee is pursuing a doctorate from the Department of Economics at
the University of Washington and was a summer intern at Resources for the Future.
This article is based in part on a presentation by Macauley
at the American Meteorological Society's 2007 Summer Public Policy Colloquium.